BUSINESS CASE – CHICHIBU 1.0 MW

BUSINESS CASE – CHICHIBU 1.0 MW

  • Hergo Sun Japan K.K has been the first non-Japanese company to be awarded a public tender.
  • In November 2015 started the construction of the plant.
  • The construction was carried out by KCCS a division of Kyocera group on the basis of a turnkey EPC contract.
  • The PV Plant entered into operation on February 27th 2016.
  • The O&M activities will be performed by the Japanese DJKSS, a joint venture of Infrastrutture Group.
Available surface
2.1 ha
Tariff
40 ¥/kWh
Production * June 2016
511,301/kwh